Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
CDBG sewer project moves toward pipe push and generator delivery; final connection expected after holidays
Summary
Staff reported the CDBG-funded Seward Springboard sewer project had the auger removed and crews expected to push pipe in the coming days, with the final generator due around Christmas and the system going live after the final manhole connections and generator installation.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
City staff reported progress on the CDBG Seward Springboard sewer project at the Nov. 18 meeting. Staff said crews had removed the auger from the boring tube and expected to begin pushing pipe the following Thursday, estimating one to two weeks to complete that section before the final manhole connection and final generator delivery.
Staff noted the final generator was expected around Christmas and that a temporary generator with wheels was currently at the pump station while the permanent unit is awaited. "Then everything will go live," staff said once the last connection and generator are in place.
No council action was required; staff said construction meetings would pause for Thanksgiving and resume Dec. 5.

