Council approves $132,695.50 payout for sanitary sewer work
Summary
Swisher City Council approved Resolution 71 to pay Dave Schmidt Construction $132,695.50 for work completed through Oct. 31 on the sanitary sewer project; council took a roll call and the motion carried.
Get email alerts on the Sewer Project topic
No spam. Unsubscribe anytime.
Council considered Resolution 71, approving payout number 7 to Dave Schmidt Construction of Cedar Rapids for $132,695.50 for work completed through Oct. 31 on the sanitary sewer project. The Mayor read the resolution details and the motion to approve payment was seconded; a roll call vote was recorded and the motion carried.
Engineer staff explained that the pay application included previously approved change orders and that the payment represented work billed through the end of October. No members opposed the payout on the record; staff will process the payment and apply previously authorized change orders to the contract accounting.