The court amended minute order 361.25 to raise the Capital Construction contract cap from $101,574 to not exceed $125,000 to cover door replacements and related work needed to meet certification standards for an eight‑bed long‑term juvenile detention facility; officials said housing juveniles locally should save outside placement costs.
Get email alerts on the Juvenile Facility Renovation topic
No spam. Unsubscribe anytime.
County Auditor Stacy Parr explained the amendment to minute order 361.25 (originally approved 08/05/2025) to increase the contract cap to a not-to-exceed $125,000 so Capital Construction could complete renovations required for certification of an 8‑bed long-term juvenile detention facility. Parr said contractors completed the work and that deficiencies (doors not up to standard) were identified during a walkthrough and corrected, with the project now complete.
Parr and others noted the certified facility will reduce reliance on out-of-county placements that can cost roughly $300 per day per juvenile; the amendment passed unanimously to avoid returning for another contract adjustment.