RPU updates council on power-supply plan; staff says city is about two-thirds of the way to 100% net renewables by 2030
Summary
RPU staff reported progress toward a 100% net-renewable electricity goal by 2030 but said the utility still needs additional capacity to replace retiring wholesale supply; staff plans an expanded RFP and market tests this year to fill the remaining gap.
Get email alerts on the Power Supply Plan topic
No spam. Unsubscribe anytime.
Rochester Public Utilities staff told council members the city’s power-supply plan balances reliable capacity for peak days with the goal of reaching 100% net renewable energy by 2030 and that about two-thirds of the renewable energy target is currently assumed under existing contracts.
Bill Bullock, who is leading the power-supply planning work for RPU, said the utility has executed several contracts, implemented battery storage agreements, and completed an interconnection agreement for Mount Simon Station at substantially lower-than-expected interconnection cost. "Our plan always has been a balance between the reliable capacity that we need to meet a peak day... and the renewable energy that we need in order to achieve the 100% net renewable goal by 2030," Bullock said.
Bullock acknowledged remaining risks — federal permitting delays for some large wind projects, uncertain future market accreditation for batteries at MISO, and tariff and inflation pressures — and said staff will issue a broader RFP to explore additional renewable, storage and contract-based options and present recommendations by the end of the year.