Willamina SD 30J superintendent warns of geotech, culvert work that could add about $120,000 to field shed project

Willamina School District 30J Board of Education · March 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Superintendent reported geotechnical issues under a planned metal shed — an exposed galvanized culvert and expansive clay — and said engineers estimate additional work "somewhere north of 120,000." Staff said the project appears in the bond and HMK has been recommended for construction management.

The Willamina School District 30J superintendent reported that geotechnical work uncovered under the proposed metal shed site will require replacing a corroded galvanized culvert and importing rock to stabilize expansive clay, a job he said could cost "somewhere north of 120,000." The district’s superintendent told the board the bond language lists the project and staff are exploring budget adjustments and contingencies to absorb the extra cost.

Board members discussed options for sleeve or culvert replacement and a possible construction-budget adjustment at fiscal year end. The superintendent said the district had already placed the metal building order before a March steel-price increase and warned rebidding could raise costs by about 25 percent. He also said the district had interviewed construction-management firms and sent an intent-to-award notice to HMK with a seven-day appeal window.

"They don't wanna just go in there and cover up that pipe with a building," the superintendent said in explaining engineers' recommendations to excavate and replace the culvert and add structural rock. He added the additional rock and sleeve work was being estimated on the high side at roughly $120,000.

The board asked for more detailed cost estimates and for staff to identify budget offsets. The superintendent said staff were reviewing maintenance accounts and possible year-end appropriations to avoid delaying the bonded project. He further recommended the board convene any needed votes quickly if HMK returns an executable contract before spring break to avoid losing the construction-management window.

Next steps: staff will pursue refined quotes, report back on contingency options and return with an appropriation request if needed.