Commissioners approve drainage improvement contract actions and change order to finalize park paving work
Summary
The court authorized final actions on a county drainage-improvement contract (GLO contract #22-085-014-D245) and approved a time-extension change order for Bill Savage Park paving and sidewalk improvements (bid 2025Dot09) after confirming ADA inspection and site adjustments.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
Calhoun County commissioners approved actions related to both a drainage-improvement project and a paving/sidewalk contract for Bill Savage Park. For the drainage project (GLO contract #22-085-014-D245), staff outlined site additions including pavement extension on 9th Street, inlet and junction box adjustments, added seal force, pipe extensions and headwall work; the court authorized the certificate and signature authority to finalize the contractor’s payment and closeout.
On a related item, staff explained that Bill Savage Park’s paving and sidewalk improvements are complete and passed ADA inspection; Change Order #3 was approved to formally add contract time that had been omitted when prior change orders were processed. The court moved and approved both items by voice vote.