Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Transportation topic

No spam. Unsubscribe anytime.

County adds $1.25M to Washington Road preliminary engineering; approves UV lining and Ridge Crossing repairs

Columbia County Board of Commissioners — Community & Services Committee; Public Works & Engineering Services Committee · July 28, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Engineering staff recommended a $1,000,000 federal and $250,000 county supplement to the Washington Road preliminary engineering agreement with GDOT, approved a $24,591 change order for 2026 stormwater UV lining and a $15,000 engineering contract for Ridge Crossing storm drain rehabilitation.

Engineering services (Titus) presented several transportation and stormwater items the committee approved on consent.

Titus said the MPO identified rollover funding and staff asked the MPO to add $1,000,000 federal and $250,000 county funds to the Washington Road widening preliminary engineering phase; he said the amendment would not change the project timeline. "This is not going to change the timeline of the project. This would just add additional funding," Titus said.

In stormwater work, staff presented change order number 1 to Cajun Construction for the 2026 stormwater UV lining projects to correct pipe sizes, increasing the contract by $24,591 to $120,250. Titus also recommended engineering services from Southern Civil Solutions for $15,000 to prepare construction documents for corroded stormwater pipes at the Ridge Crossing apartment complex. Both items were approved on consent.