Commissioners approve $97,391 West Parking Lot expansion despite questions about last‑minute change
Summary
The court approved a $97,391 contract to add 14 spaces to the Judicial Center’s west parking lot after debate about whether late design changes and cost were the best use of funds; vote was 3‑yes, 1‑no, 1‑abstain.
Get email alerts on the County Facilities topic
No spam. Unsubscribe anytime.
John Hernandez, the county engineer, told the court Fulton Construction returned a revised price of $97,391 to add 14 parking spaces at the Judicial Center’s west lot, a reduction from earlier estimates near $380,000. Hernandez said the earlier price included additional security features and the current figure reflects a narrowed scope.
One commissioner objected to adding 14 spaces at the last minute and questioned the cost-effectiveness: "I mean, this this was a design thing from the get go... I'm just wondering why we're spending $97,000 more," the commissioner said. After discussion, a motion to approve the additional parking passed with three ayes, one nay and one abstention.