Commission awards Park Potable Water contract to Dykeman Excavating

Cass County Redevelopment Commission · June 15, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

After reviewing multiple bids for the Park Potable Water project, the commission accepted staff and consultant recommendations and approved awarding the contract to Dykeman Excavating by voice vote.

The Cass County Redevelopment Commission approved awarding the Park Potable Water contract to Dykeman Excavating following a bid readout by staff. Staff member (speaker 2) recited bids for multiple contractors—listing Dykeman Excavating's Division A base bid at $3,729,900 and Division B base bid at $674,872 among others—then said staff and consultant review recommended awarding the work to Dykeman; the chair called for and received approval by voice vote.

"For Dykeman Excavating, division a base bid was $3,729,900," staff read aloud as commissioners reviewed the competitive bids. Chair (speaker 1) confirmed a motion to approve Dykeman for the Park Potable Water project; the motion was seconded and carried by voice vote. Staff noted the contract award followed advisement from HWC and a legal review to proceed.