Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Bayside Terrace topic

No spam. Unsubscribe anytime.

Bayside Terrace at substantial completion; contractor working through 114-item punch list

La Porte Drainage and Flooding Committee · August 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff reported a July 21 substantial completion walk for the Bayside Terrace drainage project produced 114 punch-list items; the contractor said 57 items remain, mostly minor (mailbox adjustments, crack sealing) with sod replacement and a scheduled concrete pour next week.

City staff said a substantial completion inspection for the Bayside Terrace project was held July 21 and produced about 114 punch-list items. Jameson told the committee the contractor reported it had 57 items left to address, with most items described as minor — raising mailboxes, sealing cracks and similar fixes — while the largest outstanding item is replacement of sod where initial placement is being replaced.

Jameson said driveway aprons and additional concrete around a new inlet are scheduled to be poured the following week and that crews will likely remain on-site about 45 more days to finish sod and close out remaining items. He also said staff have met regularly with homeowners and the contractor has corrected several sanitary-connection issues at its expense.