Bayside Terrace at substantial completion; contractor working through 114-item punch list
Summary
City staff reported a July 21 substantial completion walk for the Bayside Terrace drainage project produced 114 punch-list items; the contractor said 57 items remain, mostly minor (mailbox adjustments, crack sealing) with sod replacement and a scheduled concrete pour next week.
Get email alerts on the Bayside Terrace topic
No spam. Unsubscribe anytime.
City staff said a substantial completion inspection for the Bayside Terrace project was held July 21 and produced about 114 punch-list items. Jameson told the committee the contractor reported it had 57 items left to address, with most items described as minor — raising mailboxes, sealing cracks and similar fixes — while the largest outstanding item is replacement of sod where initial placement is being replaced.
Jameson said driveway aprons and additional concrete around a new inlet are scheduled to be poured the following week and that crews will likely remain on-site about 45 more days to finish sod and close out remaining items. He also said staff have met regularly with homeowners and the contractor has corrected several sanitary-connection issues at its expense.