Commissioners hear construction budget update for law enforcement center and library
Summary
The judge reported the law enforcement center and library construction contracts are tracking within the guaranteed maximum price, with retainage remaining; payments to architect and construction manager are close to finalization.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
County leadership provided an informational update on construction-related budget items for the law enforcement center and library. County Judge Randy Johnson told the court the county received a guaranteed maximum price from the contractor and, as reflected in the packet, "we should get even a little bit of money back" as retainage is resolved.
The judge said invoices and retainage remain but that the architect and construction manager have largely fulfilled obligations; the update was presented as information and did not require additional action. Commissioners asked clarifying questions about which funds and project codes cover the architecture and construction line items; the judge identified fund references in the packet.