Road Department outlines Webber Road paving plan, staffing needs and equipment delays

Jewell County Commissioners · August 4, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Road Department reported patching on Webber Road and proposed eventually paving six miles at an estimated 1,700 tons of asphalt per mile; commissioners discussed grader routes, potential hires and a request to give employee Jeff Cheek a raise and county pickup.

Joel Elkins, speaking for the Road Department, told the commissioners crews are patching asphalt on Webber Road and that the long‑term plan is to asphalt all six miles of the road. He provided a concrete quantity used in planning, saying it "will take 1700 tons of asphalt per mile," a figure relevant to budgeting and procurement.

Elkins raised personnel and equipment needs: he said reinstating the county's old motor‑grader route would require hiring two additional employees, and he asked that Jeff Cheek receive a raise and a county pickup to drive home, saying without him "I would be in a world of trouble." Commissioners discussed sending multiple blade operators to roads north of Esbon and the availability of an existing county vehicle that could be assigned rather than buying a new one.

Elkins also reported a nearly year‑long delay for parts needed to mount a tree‑cutter attachment; Finn Cool had not finished fabricating the mounting pieces. He cautioned that applying calcium chloride for dust control had previously made roads very slick when there was any moisture in the air.