Ottawa County approves Langram Road change order, sets May 1 completion date
Summary
Commissioners approved Change Order No. 3 with Erie Blacktop for the Langram Road CR #163 Rehabilitation Project with no change in contract amount and an updated completion date of May 1, 2026 due to weather-related delays to pavement striping.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The Ottawa County Board of Commissioners authorized Change Order No. 3 with Erie Blacktop, Inc. for the Langram Road CR #163 Rehabilitation Project on Jan. 15, 2026. The record states the change order "does not include any increase or decrease in the contract amount" and the contractor requested a revised completion date of Friday, May 1, 2026 because poor weather delayed pavement striping that must meet ODOT specifications.
The action was taken on the recommendation of the County Engineer and approved by the Prosecuting Attorney; the motion was moved by Commissioner Donald A. Douglas, seconded by Commissioner Mark E. Coppeler, and the vote was recorded as Mark W. Stahl, yes; Donald A. Douglas, yes; Mark E. Coppeler, yes.