Committee considers $200-per-day damages as Brownville Road contractor falls behind

The Police Jury of the Parish of Winn Road Committee · August 16, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Engineer Henry Shuler told the Winn Parish Road Committee the Brownville Road contractor experienced problems and the Parish could assess liquidated damages of $200 per day; the Committee said it would consider the recommendation.

The Winn Parish Road Committee discussed contractor performance problems on Brownville Road at its Aug. 16 meeting and heard a recommendation that the Parish could apply $200 per day in damages for delays.

Engineer Henry Shuler described the issues the contractor encountered and told the Committee that the Jury could implement damages of "$200 a day" for the project's delay. Committee members discussed the recommendation and did not reach a final decision at the meeting; they said they would "consider the recommendation," leaving any formal assessment to a later action.

No vote or formal penalty was recorded at the Aug. 16 meeting.