Valley Street Project design 95% complete; NDDOT asked to remove rock from right-of-way
Summary
HDR reported the Valley Street Project is 95% designed and 63% of the budget invoiced; NDDOT requested that rock be removed from the right-of-way, delaying cost-share submission until plans are revised. Temporary easement with Michael Baker is near finalization.
Get email alerts on the Valley Street Project topic
No spam. Unsubscribe anytime.
Project engineer Chris Korkowski told the Board the Valley Street Project design is 95% complete and that 63% of the total project budget has been invoiced. Korkowski said plans were submitted to the North Dakota Department of Transportation (NDDOT), which requested removal of rock from the right-of-way; as a result, plans are being revised and will not be submitted for cost share until the revisions are finished.
Korkowski and Attorney Bryan Van Grinsven said they are finalizing a temporary easement agreement with Michael Baker. The Board noted the project's potential DWR cost share could range from 0 to 25 percent based on a benefit-cost analysis; plans and specifications are expected by the end of February.