Board denies contractor time extension and considers withholding 11% for riprap not meeting specs

Ward County Water Resource Board · January 12, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

HDR recommended withholding 11% from payment application #2 for riprap that does not meet specifications; Blue Stone requested additional time for completion, which the Board denied, and the Board agreed the riprap in place does not pose a safety hazard.

Board representatives addressed a quality issue with riprap placed on several dam projects at the Jan. 12 meeting. HDR and Blue Stone were reported to be working through a riprap specification issue; HDR proposed withholding 11% from payment application #2 for riprap placed that does not meet specifications and stated the riprap already in place "doesn't pose a safety hazard."

Blue Stone submitted a request for additional time with supporting material; because most work is expected to be complete in January and the substantial completion deadline is April 1, 2026, Jason Zimmerman moved to deny the request and Roger Kluck seconded; the motion passed 5-0. The Board discussed remaining budget amounts: HDR reported about $93,000 remained for design work (including Burlington Dam #3) and about $50,000 remained in the construction budget.