Commissioners approve $156,637 change order for County Road 17
Summary
Clark County commissioners approved change order #2 for County Road 17, adding $156,637 for extra cement required by a geotechnical mix design; vote was unanimous and the decision was moved by Commissioner Sara Gjerde.
Get email alerts on the Roads topic
No spam. Unsubscribe anytime.
Clark County commissioners on Aug. 20 approved change order #2 for County Road 17 to cover extra cement required by a geotechnical mix design. The board recorded the cost as $156,637.00 and voted unanimously to approve the change order.
Highway staff Tobin Morris and HS Eggleston provided the update to the commission and described the geotechnical adjustments that drove the additional cement requirement. Commissioner Sara Gjerde moved to approve the change order; Commissioner Francis Hass seconded the motion. Voting aye were Wallace Knock, Francis Hass, Sara Gjerde and Terry Schlagel. The minutes list the total amount as $156,637.00; the board did not record any dissenting votes.
The change order was described in the meeting as necessary to meet the engineered mix design; the minutes note the funding impact but do not specify the funding source. The item will be reflected in upcoming highway project accounting and the commission will consider budget implications during normal budget review.