County receives water and wastewater project update, reservoir designs submitted for review
Summary
W/W Associates told the board that the raw water line (Division 2) recently crossed Fredericksburg Road and work is advancing toward Vista Heights Road; reservoir erosion‑control plans were submitted and the plant was redesigned from 3 MGD to 2 MGD with value engineering ongoing.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
W/W Associates briefed the Greene County Board of Supervisors on progress for several water and wastewater projects, reporting steady construction activity and upcoming permitting steps.
The firm said Division 2 of the raw water line has crossed Fredericksburg Road and crews are progressing toward Vista Heights Road; the raw water pump station site is being prepared and rock borings have been completed. Reservoir erosion and sediment control plans were submitted to the county for review and the team plans to submit design drawings to the Department of Conservation and Restoration (DCR) and the health department soon. The water‑treatment plant design has been revised from 3 million gallons per day to 2 million gallons per day and staff are pursuing value engineering.
"We're thinking 6 weeks from now, he might be done, weather permitting," the presenter said when describing progress on the raw water line crossing. The firm also reported that final plans for a wastewater improvement (Stammeringale) were submitted to DEQ and that a site plan had been filed with the county for advertising.