Pre-construction plan set for Road 1010 bridge replacement; Notice to Proceed April 20

Roosevelt County Board of Commissioners · April 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Interstate Engineering and Bishop Inc. presented plans to replace a 26-foot timber bridge with a 25'5" x 10'2" aluminum box culvert, with a Notice to Proceed on April 20 and substantial completion targeted for May 18, 2026.

John Bach of Interstate Engineering outlined a pre-construction plan to replace a 26‑foot timber bridge on Road 1010 with an aluminum box culvert measuring 25 feet 5 inches by 10 feet 2 inches. Bach reported a 30‑day completion timeline, with Notice to Proceed scheduled for April 20, 2026, and substantial completion targeted for May 18, 2026. Construction responsibilities include compliance with local, state and federal regulations, site safety, dewatering using pumps and an earthen dam, and ballast material for structural fill consistent with prior projects.

Contractor representatives said staging may use the McCabe shop, traffic control and detour signage will be placed at key intersections, and the contractor will notify Chuck Hyatt at Bainville School regarding temporary bus route changes. Bishop Inc. will coordinate salvage and handling of existing bridge timbers with the Road Foreman.