West thickened sludge pumping station nearly complete; east-side work to follow

Rensselaer County Sewer District No. 1 · February 25, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Construction of the west thickened sludge pumping station is nearing completion; the district is awaiting concrete pads and final electrical connections before beginning east-side work and replacing skimmings building equipment once valves arrive.

District staff reported that construction of the west thickened sludge pumping station is nearing completion, and that the project is awaiting concrete pads for pumps and final electrical connections. Once the west side is complete, work on the east side will begin.

The minutes also note that skimmings building equipment replacement is anticipated to commence once new valves are received, expected in March. The update indicates ongoing construction progress but does not list final completion dates or costs in the Feb. 25 minutes.