Sewer district schedules bypass piping; Siemens meeting to review decant tank size and valves
Summary
District staff said bypass piping to route skimmings to blended sludge tanks is scheduled the week of March 2, 2026; Siemens will meet with district staff to discuss replacing a delivered 4,300-gallon tank with the originally contracted 6,000-gallon tank and to review valves and sensors.
Get email alerts on the Plant Equipment topic
No spam. Unsubscribe anytime.
The sewer district reported that skimmings decant tank bypass piping is scheduled for installation during the week of March 2, 2026. The bypass will temporarily allow skimmings to be pumped to the blended sludge tanks until a decant tank is installed.
Minutes record that Siemens requested an additional meeting to discuss the decant tank replacement and related valves and sensors; the minutes state the meeting is to take place on Friday, Feb. 27 (the minutes list 2025, which appears to be a year notation error in the record and has been corrected here to 2026 for consistency with the meeting timeline). The minutes further note the district is considering replacing a delivered 4,300‑gallon tank with the 6,000‑gallon tank originally specified in the contract, and that new valves are expected to arrive in March before skimmings building equipment replacement begins.