Doniphan County road office tracks storm damage, reviews culvert bids and reports bridge funding denial
Summary
Road Office Manager Lindsay Norris said the county is documenting storm damage for possible FEMA assistance, reported a washed-out 15" tube and presented temporary work agreements for Diamond Springs Road box culvert repairs; the county was not awarded FY27 bridge replacement funding and a single culvert bid of $29,250 was received and tabled.
Get email alerts on the Road Maintenance topic
No spam. Unsubscribe anytime.
Doniphan County Road Office Manager Lindsay Norris told commissioners June 8 that staff are tracking storm damage from heavy rainfall the week of June 1, 2026, in case a disaster declaration and FEMA funding become available. Norris also reported a washed-out 15" tube on 275th Road and said contractor Pat Urban was contacted to assess the site.
Norris presented temporary work agreements from adjoining landowners for a box culvert repair on Diamond Springs Road that the county road department will perform using rented equipment. The board also held a bid letting for a 200' x 24" crossroad culvert on Randolph Road and opened a single bid from Engemann Drainage Co., Inc. for $29,250; the board tabled action pending review. Separately, Norris advised Doniphan County was not awarded bridge replacement funding for FY27 through the Kansas Local Bridge Improvement program or the Off-System Bridge program.