Siemens to supply valves, sensors for gravity thickener monitoring
Summary
Siemens committed to supply valves and sensors for the gravity thickener system so the plant can continue using the original overflow line while monitoring thickener levels to reduce flood risk.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Meeting minutes from March 25, 2026 record that Siemens has committed to procure and install valves and sensors for the gravity thickener system. The valves are intended to preserve use of the original gravity thickener overflow line while added sensors will monitor thickener levels to help prevent flooding.
The minutes do not specify a contract value, procurement timeline, or installation completion date for the Siemens work. No formal vote on the Siemens commitment was recorded in the district meeting minutes; the entry is a staff-level project update.