Commissioners approve 50/50 cost-share with Georgetown for Maplewood lift-station drainage work
Summary
The Board approved Change Order No. 5 for Maplewood lift-station drainage improvements, with Georgetown and Floyd County each agreeing to pay 50% of the $7,625.00 cost; the motion passed unanimously.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Nick Creevy, Director of Building and Development Services, presented Change Order No. 5 for the Maplewood lift-station (LS) drainage improvements and explained an interlocal agreement with the Town of Georgetown. Under the agreement, Georgetown will pay 50% of the cost and the county will pay the other 50%; the county's share is $7,625.00. Commissioner Frank Loop moved to accept the interlocal agreement; Jason Sharp seconded and the motion passed unanimously.
The agreement addresses localized drainage near the Maplewood lift station and formalizes cost-sharing between the county and the town. Creevy did not provide a project timeline or funding source attribution during the discussion; commissioners recorded approval of the cost-share agreement.