Taos County approves $115,000 change order to shore historic courthouse after water damage

Taos County Commission · September 3, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Contractors reported structural water damage at the historic county courthouse requiring shoring and scaffolding; the commission approved a change order of about $115,000 to shore east and west walls and allow roof repairs to proceed safely.

County construction staff reported significant structural damage to sections of the historic county courthouse caused by water infiltration, and requested a change order for shoring and scaffolding to stabilize the building so roof work and other repairs can continue.

A construction manager described the damage to the southeast and southwest corners and recommended shoring from the ground to the roof line along the affected walls. "It's going to require shoring on those east and west walls from the 1st Floor to the 2nd Floor, from the 2nd Floor to the roof," the manager said, and estimated a change order for approximately $115,000.

Commissioners approved the change order by roll call. Staff said the work is needed to make the building safe for workers and to prevent loss of historic fabric; they will coordinate the change order with the larger courthouse renovation funding and contract adjustments already discussed during the meeting.