Construction update: cameras, furniture near completion; internet order in technician phase
Summary
Officials reported courthouse security camera placement and furniture are nearly finished; the county's internet order is in and currently in the technician phase, with vendor follow-up planned to confirm schedule.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
County officials updated commissioners on courthouse construction, security equipment and internet service provisioning.
A commissioner said camera placement and furniture walkthroughs are nearly complete and that the architect and district court approved the security plan for the east vestibule. On connectivity, the commissioner said, "I have received confirmation that our order is in... we're in the technician phase," and staff said they would press the vendor and consider engaging NextLink as a backup to secure timely service.
Staff also noted small punch-list items (lobby chairs color mismatch and remaining furniture pieces) and plans to reconcile those items with contractors. No formal action was taken; staff will follow up with the vendor and report updates to the court.