Summary

Presenters estimated demolition of Center Elementary at about $2.73M and proposed adaptive reuse scenarios ranging from ~$8.2M (office) to ~$16.4M (senior housing); the team said those costs are generally not eligible for state school construction reimbursement.

As the committee considered consolidated options, architects presented reuse and demolition scenarios for existing school buildings.

Jeff Wazinski said demolition of Center Elementary would run roughly $2,728,000 if the town chose to remove the building and convert the playfields to community use. Adaptive‑reuse estimates for Center included about $8.2 million to convert to light office use and about $16.4 million for a full conversion appropriate for senior housing (additional plumbing and code changes increase cost). Wazinski emphasized those reuse options were presented at high level "order of magnitude" pricing and were not included as reimbursable items in the school‑construction grant calculations.

For Hall Memorial, the team modeled preserving roughly 24,000 sq ft of original building fabric while removing about 43,000 sq ft; Scott Feldman warned the state would likely reimburse only the portion directly tied to educational use and might not fund full restoration without a strong program tie. The presenters framed these options as community choices that could be explored further if a consolidated option that removes the existing school inventory is advanced.