Summary

Architects compared mechanical systems (propane baseline, VRF/air‑source heat pumps, chilled beams with geothermal) and a 620 kW photovoltaic option; committee discussed adding a geothermal yes/no question to community polling, noting upfront bonding and rebate timing affect mill‑rate impact.

Architects told Willington officials that energy‑system choices materially change lifecycle costs and payback when combined with expected state reimbursement and utility rebates.

Jeff Wazinski presented three baseline mechanical systems and a ~620 kW photovoltaic array priced at approximately $2.5 million. He said that when the higher state reimbursement is applied, “your payback’s less than 2 years for any, you know, the most extreme system,” and that utility rebates can be substantial. The presenters also explained that rebates typically arrive after a year of operation, so the rebate amount must be bonded in the project budget.

Committee members pushed for clarity about whether geothermal should be presented to voters. One member asked, “Can we put, like, a yes or no question if people want geothermal on that polling?” The committee agreed it could include a simple yes/no poll item, while cautioning that including geothermal in the referendum number would require the design team to finalize operational‑cost estimates and the grant packet to reflect the exact referendum amount.

Presenters said geothermal can lower long‑term operating costs but increases upfront bonding requirements; they recommended further technical analysis before locking it into the referendum number.