PBOT explains phased approach to Burnside corridor work after bridge funding fell through

Public Works Committee · July 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

PBOT told the committee it will address Burnside’s needs through a three-phase, multi-year approach after funding for a larger Burnside Bridge project fell through, prioritizing segments where prior investments reduce the scope of additional work and providing opportunities for community input.

Councilors raised constituent concerns about planned work on the Burnside corridor; PBOT said the corridor is complex and that a previously planned bridge project lost funding, changing the city’s approach. Millicent Williams said she instructed staff to identify a way to address maintenance needs and safety while phasing work to allow community feedback and to match available funding.

Gabe Graff explained phase one focuses on West Burnside between 15th and 20th where prior corner accessibility investments mean less additional work is required and paving there "buys us time to continue to look at the rest of the corridor." PBOT framed the approach as three phases over three years to allow iterative community input and additional analysis for later phases. Staff acknowledged sidewalks are narrow in portions of the corridor and that safety and circulation challenges will require further study and public engagement.

Next steps: PBOT agreed to provide the committee and affected council offices with more detailed phasing rationale and analysis so members can respond to constituent concerns; the bureau will also consider alternative funding and reimagining options for the corridor as part of continued outreach.