Bridge deck poured; contractor faces $1,250/day liquidated damages

McCook County Commission · October 8, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County highway superintendent reported bridge deck for bridge #44‑010‑185 was poured after a scheduled Sept. 1 completion date, and liquidated damages of $1,250 per day have begun to accrue.

Highway Superintendent Travis Raap told the commission that the deck for bridge #44‑010‑185 was poured last week, noting the original completion deadline had been Sept. 1, 2024. Because the project missed the contract completion date, liquidated damages of $1,250 per day have started to accrue.

The commission did not take additional action at the meeting but recorded the status for county project oversight. The highway department will continue monitoring contractor progress and the application of daily liquidated damages per the contract terms.