Engineer says DEP requires public-water permitting and 48‑hour pumping test for Gamma project
Summary
McCarty Engineering told the commission that DEP determined a new or relocated well for Gamma’s 847 Green Street project meets the threshold for a public water supply; DEP conditions include a 48‑hour pumping test (min. 1.1 gpm / design ~1,190 gpd), PFAS testing, Zone‑1 delineation, and filling an old shallow well; the NOI hearing was continued so the town engineer can review.
Get email alerts on the Gamma Noi 847 Green Well topic
No spam. Unsubscribe anytime.
McCarty Engineering, representing Gamma, presented an amendment request for DEP file 1600681 related to a planned building and associated utilities at 847 Green Street. The firm told commissioners that DEP’s review determined the project triggers public-water-supply permitting and that DEP approved the proposed well location subject to detailed conditions.
The presenter explained DEP’s specific testing and reporting requirements: the pumping test and water‑quality sampling must follow MassDEP guidelines, the pumping test must run at a minimum rate of 1.1 gallons per minute (to demonstrate an approved rate equivalent to roughly 1,190 gallons per day), precipitation should be measured on-site, and PFAS (PFOS/PFOA) testing will be required. The presenter also said DEP wants the project’s Zone‑1 ownership demonstrated and the existing shallow well on the property filled. Commissioners asked for the town engineer (Rob) to review the submission and agreed to continue the hearing to July 27 so the town can provide input before a final local decision. "The pumping test and water quality sampling shall be conducted in accordance with DEP's guidelines," the presenter said.