WSDOT notifies Colfax of four-year delay to SR 195/SR 26 bridge project; city plans tree removals and notes FEMA open house

Colfax City Council ยท May 5, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City Administrator Matt Hammer told the council WSDOT has informed Colfax that the SR 195/SR 26 Bridge Project will be delayed by four years; Hammer also said crews will remove trees on Main Street with WSDOT traffic control assistance and reminded the council of a FEMA open house May 8 at 6 p.m.

City Administrator Matt Hammer reported that the Washington State Department of Transportation (WSDOT) has notified Colfax that the SR 195/SR 26 Bridge Project will be delayed by four years. Hammer presented this as new scheduling information from WSDOT and did not provide project funding or next-step details during the May 5 meeting.

Hammer also said the city will remove trees on Main Street and that WSDOT will assist with traffic control during those operations. He reminded councilmembers that a FEMA open house is scheduled for Thursday, May 8 at 6 p.m. at the Whitman County Public Service Building.

No formal action was taken at the meeting on the bridge schedule; Hammer said staff will continue coordination with WSDOT and will brief the council on implementation or scheduling changes as information becomes available.