Council awards contract to rebuild Paintbrush Park dam and downstream repairs
Summary
Council approved a roughly $3.35 million low bid (53 Corp) plus engineering oversight and contingency to reconstruct the Paintbrush Park dam and stabilize downstream channels; staff said the pond will be drained and cautioned residents about unpleasant odors during construction.
Get email alerts on the Stormwater Dam Reconstruction topic
No spam. Unsubscribe anytime.
Council approved a construction contract to reconstruct the Paintbrush Park (6400 East Tributary) dam and perform downstream stabilization and drainage improvements, accepting the low bid submitted by 53 Corp and authorizing related engineering oversight and contingency funds.
Mark described the dam as more than 10 feet tall and not built to current jurisdictional standards, making reconstruction necessary for public safety and to preserve the pond as a local firefighting resource. "This was the low bid 3,350,000 from 53 corp," he said, adding engineering oversight costs and a contingency that bring the total project authorization to just over $4,000,000. Staff noted the pond will be electro‑fished and fish relocated by outside entities and warned residents the pond will be drained and "it will stink" while exposed sediments dry. The council approved the resolution by unanimous vote.