Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Wastewater topic

No spam. Unsubscribe anytime.

Public works: new lagoon system online; crews finishing grading, fence work

City of Seneca City Council · May 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public Works reported the city—rought the new wastewater lagoon system online April 7–8 and is about 80–90% complete with gravel, finish grading, seeding and fence installation. Council discussed using initial liquid volumes or transfers from old lagoons to hold liners and postponed a meter relocation while sourcing a plumber.

Public Works lead Shane Koppel told the council the new lagoon system went online April 7–8 and that crews were "80-90% completed" with the project; remaining tasks included gravel, finish grading, seeding and erection of the perimeter fence. Koppel said the fence installation is underway and proposed widening the dump gate to improve access.

Councilors discussed operational steps to stabilize the lagoon liners, such as increasing the initial liquid level by transferring liquids from the old lagoons or by pumping water from the golf irrigation well. Koppel said the project to move an existing meter and water line on Higbie's property on Shirttail Creek Road is delayed while the city seeks an agreeable plumber. The council also reviewed policy considerations for not shutting off water service for nonpayment during COVID-19 restrictions and the need to send nuisance property notices.