Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Parks Infrastructure topic
No spam. Unsubscribe anytime.
River's Edge project moves forward with parking, ADA and skate-park work
Summary
Superintendent Marla updated the board on River's Edge improvements including new light poles and netting, expanded parking with a mix of asphalt and gravel, six accessible parking spots, amphitheater ADA seating, and planned skate‑park and pump‑track earthwork beginning after August 1.
Get email alerts on the Parks Infrastructure topic
No spam. Unsubscribe anytime.
Marla, superintendent, told the Consuel Parks and Recreation Board that River's Edge construction is progressing: light poles and netting are installed, a playground area will sit in front of the concession stands, and new walking paths will connect fields and amenities. She said the main parking out front by Veterans Memorial will be asphalt while the lane parking will be gravel, and "this whole lot right here will be asphalt," describing where vehicles will pull in and park.
Marla also described accessibility work at the amphitheater: additional concrete seating and dedicated ADA spaces were added per a prior state grant request. She said fencing for the skate‑park area and playground removals will begin August 1, after which earthwork and installation of a deep bowl skate feature and a pump track will proceed. The board heard that the planned configuration aims to balance vehicle access, spectator circulation and ADA-compliant seating for events.

