Board approves irrigation repairs tied to Seaside & Master Drainage Project (not‑to‑exceed $15,000)
Summary
Hole Montes presented a revised drainage scope; the board approved an Irrigation Concepts change order to repair damaged wiring and raise seven to eight irrigation heads in a not‑to‑exceed amount of $15,000.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
District Engineer Charlie Krebs presented a revised scope for the Seaside & Master Drainage Project, noting the revision will allow operations staff to make later changes while preserving the original intent. MRI expects construction to begin in two to three weeks.
Mr. Krebs also presented ancillary irrigation costs from Irrigation Concepts: $4,002.50 to repair damaged wiring and about $1,300 each to raise approximately seven to eight irrigation heads. On a motion by Kurt Blumenthal, seconded by Bob Schultz, the board unanimously approved the change order in a not‑to‑exceed amount of $15,000.