Board approves $192,719.77 in HVAC contract adjustments for WMS project

Allamakee Community School District Board · July 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved CARs 12, 20 and 21 for the WMS HVAC project totaling $192,719.77 and received a Superintendent update on the broader HVAC project; the motions carried unanimously.

Superintendent Jay Mathis updated the board on the district HVAC project, and the board approved Contract Authorization Requests (CARs) 12, 20 and 21 for the WMS HVAC work, with John Palmer moving and Beth Shafer seconding the motion. The three CARs total $192,719.77 and the vote was all ayes.

The board did not provide line-item detail for each CAR during the meeting minutes; the approval authorizes the specified additional contract amounts for project execution and will be processed through the district's procurement and finance offices.