Board signs multiple change orders and a design amendment for park projects; Chapel Hill cost increases pegged at $52,247.19

Board of Parks and Recreation for the consolidated city of Indianapolis · June 23, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved several construction actions: a $11,615.09 deductive credit for Eagle Highlands playground work, a $22,806 amendment to DLZ's design contract, a $55,820.17 change order for Gustafson Field, and a $52,247.19 final change order for Chapel Hill Park, bringing Chapel Hill's contract to $1,858,247.19.

Board members approved a batch of construction and design items affecting several parks at the June 23 meeting.

Tony Hibbert, construction program manager for Indy Parks, described a deductive change order that produced a $11,615.09 credit for playground improvements across multiple parks after a parking redesign reduced required infrastructure. Staff also requested an amendment to the professional services agreement with DLZ Indiana LLC adding $22,806 and nine months to the contract term after a state stormwater rule change made certain designed stormwater infrastructure unnecessary; Ben Jackson, principal planner, said removing the infrastructure would lower construction costs even as design fees rose from $478,848 to $501,654.

Hibbert introduced Norcon Incorporated for Gustafson Field work and asked the board to approve change order #1 for $55,820.17 to finish site work and install a wood fence around a new gravel parking lot. He also summarized final change order #2 for Chapel Hill Park, listing unexpected issues including a relocated splash pad drain, an open-cut waterline tie-in requiring a temporary road closure, and a corroded culvert; that change order adds $52,247.19 for a new contract total of $1,858,247.19. Each of these memos was approved by voice vote.