Board ratifies final change order for Michigan–New York conversion, reduces contract cost and adds 699 days to completion

Board of Public Works · June 24, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Board approved Change Order No. 2 for ST26054 with Reith Riley Construction, decreasing the contract by $981,785.08 to a new not‑to‑exceed $15,161,214.92 and adding 699 days to substantial and final completion dates.

Nathan Sheets presented change order number 2, described as a final quantity true‑up and accounting for a series of work directives on the Michigan and New York two‑way conversion project. He told the board the change order reduces the contract by $981,785.08 and adds 699 days to substantial and final completion dates, yielding a new not‑to‑exceed amount of $15,161,214.92.

A board member asked whether the decreased funds would be reallocated; DPW staff said the money returns to DPW 'coffers' and can be redirected to other projects. The board voted to ratify final acceptance and the change order.