HNW project manager explains delays as council weighs $232,500 in liquidated damages
Summary
John Reneck of HNW Contracting described weather, soil conditions, subcontractor scheduling and equipment lead times as causes of project delays; the engineer reported liquidated damages of $232,500 on the Eastside West Station project and said final documents and conversations with the contractor are pending.
Get email alerts on the Construction Contracts topic
No spam. Unsubscribe anytime.
John Reneck, vice president and project manager for HNW Contracting, told the council the Eastside West Station project experienced multiple delays caused by poor soil conditions, winter weather, subcontractor no-shows and equipment lead times. He outlined a change order for additional unclassified excavation and said the contractor adjusted schedules to mitigate the issues.
"We had quite a few delays that were just outside of our control," Reneck said, describing snow, soft spots in embankments and subsequent rework that pushed schedule milestones. He said some subcontractors did not complete punch list items until months after initial turnover and attributed part of the delay to global equipment lead times.
The city’s consultant confirmed the project has liquidated damages assessed at $232,500 and that final documents have been prepared and forwarded to H&W (contractor). The consultant said the city would invite the contractor for a conversation but did not expect a resolution at this meeting; council members asked staff to seek an official written response and follow up at the next meeting.
The exchange was framed as a factual briefing and request for the contractor’s perspective; no formal finding or adjustment to the damages amount was adopted at the meeting.