Board approves $6,875 for concrete replacement at Stump Field
Summary
The board approved a $6,875 contract with Matrix Excavation LLC to replace damaged concrete at Stump Field before paving; materials procurement at an estimated municipal rate was included in the motion.
Get email alerts on the Parks Maintenance topic
No spam. Unsubscribe anytime.
Board member (S7) moved and the board approved expenditures to repair a damaged concrete section at Stump Field ahead of paving. The motion authorized $6,875 to Matrix Excavation LLC for excavation and installation and included authorization to purchase concrete at the municipal/discountrate (transcript referenced an example price of about $392.40 per unit). Supporters said the repair is necessary to avoid more extensive work later and that funds would come from road-maintenance line items.
Staff said the contract would be awarded following final administrative steps and that the work is to be scheduled promptly to meet the paving timetable. The board recorded the motion and asked staff to return with a brief confirmation of funds and scheduling.