Council authorizes engineering design funding agreement for Big Creek Dam No. 2 spillway repairs

Newport City Council · March 2, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved an intergovernmental agreement with the Oregon Water Resources Department to fund design work for repairs to the Big Creek Dam No. 2 spillway; staff said the city will pursue design with Jacobs Engineering and can recover approximately $81,640 under the agreement.

The council approved an intergovernmental agreement with the Oregon Water Resources Department to support design work for repairs to the Big Creek Dam No. 2 spillway after state annual inspection identified degraded conduits.

Todd Drage of the engineering department said the 90‑inch spillway and a 30‑inch underdrain are in disrepair; staff have retained Jacobs Engineering for an alternatives analysis and will use Jacobs for the upcoming design work. Drage said the agreement will allow funding recovery of approximately $81,640 for the design. He described the planned repair as a slip‑lining of corrugated metal pipe conduits and said the work is a distinct, near‑term repair separate from seismic mitigation projects planned for a future date. Council authorized the city manager to sign the agreement by voice vote.

Council members pressed for clarity on whether the repair was urgent; staff said the conduits have been flagged in annual inspection for four years and the repair is necessary to meet performance specifications.