Engineers present two concept paths to address seismically vulnerable Big Creek dams

Newport City Council · April 6, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Jacobs Engineering presented an alternatives analysis for Newport’s Big Creek dams, recommending two concept-level paths — remediate both dams or remove Big Creek 1 and remediate Big Creek 2 — and urged further studies, state consultation on fish passage, and a refined funding plan ahead of an April 20 report.

Engineers from Jacobs Engineering told the Newport City Council on April 6 that both Big Creek dams are not seismically stable and that the city must choose a path forward with the state soon. "OWRD has also asked that to agree to a selected option or a path forward by May 1," Nathan McCullough, a consultant with Jacobs Engineering Group, said as he summarized the alternatives analysis and regulatory timeline.

Jacobs presented two concept-level alternatives for further development. Alternative 3A would remediate both dams (stabilizing berms and ground-improvement columns) and retain current storage capacity. Alternative 3B would remove Big Creek 1 and remediate Big Creek 2, restoring roughly a mile of stream channel but reducing on-site storage and increasing reliance on the Siletz River. McCullough said remediation-only costs (without fish passage) were roughly $29.4 million in Jacobs’ high-level estimate, while adding fish passage could raise combined project totals substantially. He cautioned the estimates are order-of-magnitude only and that costs could range from roughly half to twice the numbers presented.

Counselors pressed on specifics including whether the state would allow lower-hazard reclassification, the feasibility of lowering pools to reduce remediation needs, and what tradeoffs would mean for water supply. Brad Phelps, also on the Jacobs team, framed the problem: "You have a right now issue and a now issue," emphasizing the immediate life-safety and seismic concerns followed by long-term water-supply needs.

Staff said they will bring a financial overview to the April 20 council meeting and that the alternatives will be advanced to concept-level design and additional study if council directs. The council closed the public portion of the work session and moved to executive session after the presentation; Jacobs will return with more detailed cost and permitting analyses and consultations with state agencies.