La Cygne pursues fixes for aging water system: pumps, sludge ponds and RWD #3 interconnect

La Cygne City Council · July 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

After repeated pump failures and high post-storm flows, La Cygne officials approved a new ABS lift-station pump, contracted McElreath to clean water treatment backwash ponds, and awarded an interconnect construction contract to Lathrop Construction to improve supply resilience.

City leaders prioritized water-system repairs across 2013 after a string of equipment failures and storm-related strains on the plant.

Public Works Superintendent Jim Johnson reported repeated incidents: river pump voltage issues, several main breaks in late October that required emergency repairs, and persistent accumulation in the water-treatment pond system. On Dec. 4 the council approved purchase of a new 15‑horsepower ABS pump for the park lift station ($8,061 plus freight) rather than rebuilding a worn Flygt pump; members cited the new pump’s warranty and parts availability. The council also accepted a $15,000 proposal from McElreath Construction to clean two backwash/sludge ponds at the water plant, with work to be scheduled around weather and contractor availability.

Separately, the council awarded an emergency interconnect contract with Rural Water District #3 to Lathrop Construction for $14,200 to improve redundancy in the city’s supply (contract awarded Aug. 21). That interconnect was rebid in summer 2013 and began when materials arrived.

Why it matters: Repeated low‑flow episodes and storm-related main breaks have exposed operational vulnerabilities that affect public supply reliability; council action aims to improve redundancy and reduce the risk of future boil-water advisories or extended outages.

Next steps: McElreath will proceed with pond cleanout per the contract; the city will install the new ABS pump and continue scheduled inspections. Public Works will complete MESA cathodic-protection diagnostics and follow the KCC-required leak-survey remediation plan.