Commission approves multiple construction change orders, including conductor replacement at Southeast Substation

Madison City Commission · July 21, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The commission approved a series of construction change orders affecting the Southeast Substation, Eagan Avenue reconstruction, Northwest 5th Street bridge back wall repairs, and Madison utility/street segment 9; total individual change orders ranged from a $7,950.73 back‑wall repair to a $19,976.54 annunciator replacement, most costs covered by construction allowances.

Commissioners approved a slate of construction change orders covering electric substation work and several street and utility projects. Mike explained that the Southeast Substation work required a new continuous conductor because reused jumpers had short, crimped ends that would create weak spots; that change order totaled $9,829.94 and was covered by the construction allowance so the contract price did not change. He also described an annunciator replacement and associated fill plates at the substation ($19,976.54) and a testing subcontractor increase that raised one sub‑item by $6,676.31.

Ryan presented roadway change orders: during Eagan Avenue excavation crews found an isolated pocket of weak soil requiring 422 tons of crushed recycled material at $29/ton (change order $12,238) to stabilize the pavement base. Repairs to the Northwest 5th Street bridge back wall added $7,950.73 and a final balancing change order on Madison Utility & Street Improvements segment 9 produced a net credit of $14,338.47, bringing that contract to $305,013.69. For each item staff explained the technical need and funding source (construction allowance or project budget) before motions were made and carried.