Road and Bridge superintendent reports culvert progress, bridge repair and tight schedule
Summary
Mark reported multiple box culvert projects progressing (including a triple-14 box on Dogwood/82nd), a roadway to be reopened by Friday pending seat work, recent bridge deck damage patched after a tractor incident, and weather-related delays that may push final work into next week.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
Mark, the Road and Bridge representative, gave a detailed progress report on multiple concrete box culvert projects. He said the box on 82nd at Highway 41 has been backfilled and "that road will be opened up by Friday," and that Chestnut just east of Southwest 100th was completed. He noted foundation and wall pours are done on other sites and that deck pours are pending favorable weather.
Mark warned crews have contended with repeated heavy rain that required pumping foundations and may slow work into next week. He also reported a bridge deck was damaged when a tractor drove over it; crews patched the deck using a high early strength concrete and expect to reopen the site by Friday. Mark said some culverts were sized as triple-14 while others near Sites Corey may size to triple-12 and that surveys are ongoing to confirm whether a box or bridge is required for certain crossings.