County engineer reports 2,320 feet of erosion on Ditch #30; riprap repair estimated at about $107,000

Big Stone County Board of Commissioners · August 5, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County Engineer Jorden Roggenbuck told the Board that roughly 2,320 feet of bank erosion were reported along County Ditch #30 and recommended installing riprap to stabilize the bank, estimating the work at about $107,000; he displayed maps and video of the affected reaches.

County Engineer and Drainage Inspector Jorden Roggenbuck reported at the Aug. 5 special meeting that approximately 2,320 feet of bank erosion have been reported along County Ditch #30 and recommended installing riprap to stabilize the banks. Roggenbuck presented maps and video footage of the areas needing repair and a watershed map to show contributing drainage areas.

Roggenbuck estimated the riprap stabilization project would cost about $107,000. Commissioners and landowners discussed the scope and condition of the erosion; the board later agreed to carry out emergency stabilization work first and defer the full repair until after a redetermination of benefited acres is completed.