City refines $13M-plus streets and sidewalks plan; Moore rehab estimate falls to $4.2M

Bay City Council (budget workshop) · May 12, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public works staff outlined a multi-year streets and sidewalks program emphasizing complete-streets reconstruction, prioritized resurfacing and drainage work. Moore subdivision's street estimate was lowered after design changes; staff flagged delays to Highland work to relocate utilities.

Staff presented a five-year investment strategy for streets, sidewalks and drainage, reporting more than $13 million anticipated in project costs for 2027 and explaining prioritization methods tied to pavement condition index (PCI) and citizen requests.

"The street reconstruction costs went down from a $4,800,000 estimate last year to 4,200,000 this year," the public-works presenter said, noting that some segments may be done with mill-and-overlay instead of full reconstruction after additional engineering analysis.

Staff described the Moore subdivision as designed and awaiting construction funds and explained that Highland's street work will be delayed about a year because water lines and meters in rear-alley easements need relocation into the street. The consultant-driven prioritization relies on PCI scores and counts of work orders and citizen feedback.

On sidewalks, Gabriel said the city has a CDBG sidewalk grant application for up to $1,000,000 focused on downtown gaps, school routes and the Texas Theater area and that staff is developing a multimodal connectivity plan to coordinate grant and local spending priorities.

Council members asked about funding sources. Staff said funding comes from operational budgets, street reserves and occasional park-property sale proceeds (subject to an ordinance requiring proceeds to return to parks). Staff offered to return with more detailed material costs and timeline breakdowns at a future workshop.