Balch Springs reports $6.4M trail project at 60% design; easement talks next

Balch Springs Industrial and Economic Development Corporation Type A · March 16, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff said the city’s $6.4 million trail project connecting Segal Road, Oak Ridge, Irvin Park and Pioneer is at roughly 60% design; staff has reached out to impacted parcel owners and will schedule easement meetings ahead of a likely 2027 construction start.

Economic development staff reported that the planned $6,400,000 trail project linking Segal Road, Oak Ridge, Irvin Park and surrounding corridors has reached approximately 60% design and that the city held a kickoff meeting with the construction partner. Staff said they would meet individually with property owners to secure necessary easements before construction.

The project was described as a partnership with the county and a state transportation authority for design and potential funding; staff indicated construction was likely to begin around 2027 once easements and final agreements are secured. The board received the update and staff said further property‑level outreach would continue.