Council directs staff to return with plan and funding option for Tradewind sewer extension design
Summary
After a staff presentation on the Tradewind Square sewer-extension request, council directed staff to return on May 12 with a funding recommendation to cover a proposed $250,000 design cost; staff recommended design only, citing no current funding for construction and a rough construction estimate near $2.7 million.
Get email alerts on the Utilities topic
No spam. Unsubscribe anytime.
City staff presented the history and recommendation on a long‑standing request to extend sewer service along 58th Street to serve the Tradewind Square subdivision.
Donnie Hooper summarized the request, saying the original request dated to 2016 for roughly 1,152 homes and that the initial design funding had been reallocated in a later year. Staff reported there is currently no developer agreement and the extension is not in the utility master plan. Hooper said an initial construction estimate discussed in staff meetings this week came in at about $2.7 million and that staff's recommendation was to proceed with design only, not construction, so the city could develop shovel‑ready plans and perform an ROI analysis.
Council members pressed staff for documentation of prior commitments, asked whether the city was legally bound and discussed precedent and master‑plan standards. Williams Group representatives said the subdivision has already phased development, that prior staff conversations supported moving the project forward and provided revenue estimates they calculated for full build‑out (roughly $2.67 million in water/sewer and taxes; combined revenue figures were discussed near $4 million). After deliberation, council directed staff to prepare a May 12 agenda item identifying a funding source for a $250,000 design contract rather than approving construction funds today.
Quote (Hooper): "Our staff recommendation is that we proceed with the design of this project, not the construction at this time." Quote (Councilman Simpson): "If it's not in the master plan, we need to evaluate why it wasn't in the master plan."